Your Extension of Time Won’t Pay the Bills: Prolongation Cost Claims for UAE Contractors

Commercial & Financial Contract Administration

A contractor we speak to had just won a 60-day extension of time on a Dubai fit-out. He was relieved — the delay was the client’s, the penalty clause was off the table, and the engineer had finally conceded the programme. Then he asked the obvious question: “So when does the money come?” It didn’t. The EOT stopped a penalty. It paid him nothing for the 60 days his site had actually cost him.

This is one of the most expensive misunderstandings in UAE construction. An extension of time and the money for that time are two completely different claims, governed by different clauses, proven with different evidence, and lost in different ways. Contractors chase the EOT because it is visible and emotional — nobody wants to be the one paying delay damages. Then they leave the prolongation cost — the real cash — uncollected on the table.

AED 0 What an extension of time pays you by itself

What an extension of time actually does — and doesn’t

An EOT moves your completion date. Under the FIDIC forms most UAE contracts are built on, that is Sub-Clause 8.4 (1999 Red Book) or Sub-Clause 8.5 (2017 Red Book). Its single job is to relieve you of liability for delay damages / liquidated damages (FIDIC 2017 Sub-Clause 8.8) for the period of the extension. That’s it. It is a shield, not a cheque.

The money for the delay — your prolongation cost — is a separate entitlement. It only exists where the delay was caused by an employer-risk event (a variation, late access, late information, an employer-caused suspension). Some grounds give you time but no money — exceptionally adverse weather, for instance, typically extends the date without paying your standing costs. So the first discipline is to know, event by event, whether you are owed time, money, or both.

An EOT is a shield against penalties. Prolongation cost is the cheque. Winning the first and forgetting the second is how profitable projects quietly turn into funded ones.

What “prolongation cost” really means

Prolongation cost is the time-related cost of keeping your site and organisation standing for longer than you priced. It is not the cost of doing extra work — that’s disruption or variation. It’s the cost of simply being there for the additional days:

On-site Site staff & supervision · site accommodation and cabins · welfare · plant on standby · temporary works · site running costs
Off-site Extended performance & advance guarantees · insurances · head-office overhead · financing cost on the stretched working-capital cycle

Two principles decide how much you actually recover. First, prolongation is valued by the cost you genuinely incurred during the delay — not a tendered rate and not a round-number markup. Second — and this trips up most claims — it is assessed at the point in the programme where the delaying event bit, not at the tail end of the job. The Society of Construction Law’s Delay and Disruption Protocol is explicit on this: you look at what the delay cost when it happened, not what your site looked like in the final weeks. Get that window wrong and even a valid claim is undervalued.

The two things that quietly kill the claim

1. The notice clock

FIDIC puts a hard time bar on claims. Under the 1999 Red Book, Sub-Clause 20.1, you must give notice within 28 days of becoming aware of the event — miss it and the EOT and the additional payment can be lost entirely. The 2017 Red Book keeps the 28-day notice (Sub-Clause 20.2.1) and adds a fully detailed claim within 84 days (Sub-Clause 20.2.4). UAE tribunals and courts generally take these contractual notice provisions seriously. The uncomfortable truth: a lot of strong prolongation claims are dead on arrival because nobody sent a two-line notice in the first month.

2. The records gap

Prolongation is proven with contemporaneous records — dated site diaries, resource returns, plant logs, correspondence, the programme and its updates. You cannot reconstruct eight months of standing costs from memory when the final account is being negotiated. The claim you can prove is worth far more than the claim you merely believe in.

Illustrative example — not a real client

A fit-out contractor suffers a 90-day employer-caused delay (late handover of a floor). An EOT is granted, so no penalty. But the standing cost of those 90 days, if claimed properly, might look like this:

Site management & supervision (90 days)AED 420,000
Site accommodation, welfare & running costsAED 135,000
Plant & small tools held on siteAED 180,000
Extended guarantees & insurancesAED 95,000
Head-office overhead & financing costAED 230,000
Prolongation cost at riskAED 1,060,000

Figures are illustrative to show the shape of a claim. On a job earning a 6% margin, AED 1.06M of unrecovered prolongation is the entire profit on roughly AED 18M of turnover — gone, because the EOT was mistaken for the money.

Why this is a financing problem, not just a contracts problem

Here is where it stops being a QS issue and becomes a CFO issue. A prolongation cost you’ve incurred but not yet certified sits on your balance sheet as uncertified work-in-progress — cash you’ve already spent that hasn’t come back. Leave it unclaimed and one of two things happens: it stays stuck there as WIP that never converts to cash, or, once you accept you won’t recover it, it drops straight through to your margin as a pure loss. Either way the cash is gone — and in the meantime your overdraft is funding it. That drawdown eats your banking capacity — the same capacity you need for your next bond or your next project. One missed claim doesn’t stay in one place; it travels through the whole system:

Contract
→
Commercial
Control
→
Cost &
Margin
→
Cash
Flow
→
Funding
→
Banking
Capacity
→
Growth

An unclaimed delay leaks out of commercial control and drains everything downstream — margin, cash, and the capacity to fund the next job.

This is the APM view in one line: a contractor doesn’t have five separate problems. They have one connected system — and a prolongation claim is one of the clearest places where weak contract administration shows up months later as a cash-flow and banking-capacity problem.

What to do on your next delayed project

  • Separate the two claims from day one. For every delay event, decide in writing: are we owed time, money, or both? Never let the EOT conversation absorb the money conversation.
  • Send the notice inside 28 days. A short, dated notice protects the entitlement even before you’ve quantified it. The time bar is real; treat it as a non-negotiable site routine.
  • Record cost as it happens. Keep dated resource, plant and overhead records against the delay — so the claim is a matter of evidence, not argument.
  • Value prolongation at the right window. Price the delay where it bit in the programme, on actual cost — not a tender rate, not the final-weeks site.
  • Convert the claim to cash, not just to a number. A certified claim still has to be financed until it’s paid. Build it into your cash-flow forecast and your facility planning.

Is there money trapped in a delay on your project?

Let’s review your live contracts for EOT and prolongation entitlements you haven’t claimed — and the cash-flow and banking-capacity cost of leaving them on the table.

Book a Finance & Commercial Review

This article is general guidance, not legal advice. Contract rights depend on your specific conditions of contract (including any Particular Conditions amending FIDIC) and the governing law. Review your own contract and take advice before acting on any claim or notice deadline.