How UAE Contractors Fund Large Projects Without Draining Working Capital
Insights · Project Finance
Winning a large project should be the best day of your year. Too often it quietly becomes the start of a cash crisis — not because anything went wrong, but because of how construction contracts are built. Here is the model we use to fund big works without burning through your reserves.
The cash gap is written into your contract
Under a standard FIDIC-based contract, you bill a month’s work in a statement at the end of the period, the engineer certifies it within 28 days, and the employer pays within 56 days of that statement. Once you add the weeks spent on site doing the work before you could even bill it, that is close to three months between doing the work and being paid for it — before a single real-world delay. On top of that sits retention: commonly 10% of the contract value, half released at handover and the other half only after the defects liability period, often a year later.
Meanwhile your suppliers want paying in 30 to 60 days, your labour is weekly or monthly, and your subcontractors are already chasing. The bigger the project, the bigger the gap. In practice you are financing the employer’s project out of your own pocket until the certificates catch up.
Why “funding it yourself” caps your growth — and your risk
Most contractors cover that gap the hard way: drawing down cash reserves, stretching an overdraft, or delaying suppliers and subcontractors. It works, until it doesn’t. Every dirham of your own cash locked into one project is a dirham you cannot use to tender for the next. Stretch suppliers too far and your prices rise or your supply dries up.
And late payment is now the single biggest route to contractor insolvency in the UAE — serious enough that the 2023 bankruptcy law (Federal Decree-Law No. 51 of 2023) and Dubai’s new contracting law (Law No. 7 of 2025, which introduces financial-capacity limits for contractors) are both built around it. Funding large projects from working capital isn’t just slow growth. It is fragile growth.
Fund the project, not the balance sheet
There is a better model, and it is the one we build for contractors every day: fund each project against its own security and its own cash flows, so your working capital stays free. A construction project carries far more fundable security than most contractors use — the advance payment guarantee, the certified interim certificates, the employer’s covenant to pay, the materials on site, the plant you own. Matched to the right facility, each of these can carry the project instead of your cash reserves.
01 Mobilisation & advance-payment funding
The advance payment — often around 10% of the contract value, released against a bank guarantee — exists to fund your start-up costs. Structured properly with your bank, it covers mobilisation without touching your reserves.
02 Contract & progress financing
A revolving working-capital facility your bank sizes against the contract and its certified progress — a standing line that funds the project’s ongoing cash gap, rather than being arranged one certificate at a time.
03 Trade finance & letters of credit for materials
Fund major procurement and imports through LCs and supplier finance, so a large materials order doesn’t become a large cash outflow weeks before you are paid for the work it goes into.
04 Receivable & invoice discounting
For a specific certified certificate an employer hasn’t paid, discount that single receivable for cash now — a transactional fix when one employer is running slow, without reworking your wider facilities.
05 Retention release solutions
Replace cash retention with a retention guarantee, or finance against it, so 10% of every project isn’t frozen on the employer’s books for a year or more.
06 Equipment & plant finance
Acquire plant through asset finance or leasing rather than buying it outright with working capital you need for the works themselves.
Banking capacity is the asset you’re really building
Here is the part most contractors miss. Each of these facilities does more than solve this month’s cash gap — handled well, they build your banking capacity, and banking capacity is what lets you take on the next, larger project without blinking.
A contractor doesn’t have five separate problems. They have one connected system:
A well-administered contract produces clean commercial control, which protects your cost and margin, which produces predictable cash flow, which supports funding, which builds banking capacity, which funds growth. Break the chain anywhere and your funding costs rise or your limits stall. Build it deliberately and your capacity compounds.
That is the work we do — not borrowing more, but presenting each project and each business the way banks actually underwrite.
For one contracting group we took bank facilities from AED 14 million to AED 101 million. Across our clients we have arranged more than AED 390 million in project financing and built working relationships with over ten banks.
What it looks like in practice
Take a contractor awarded a AED 50 million project — illustrative, but typical. Mobilisation and the first three months of works might demand several million dirhams of spend before the first certificate is ever paid. Funded from reserves, that is most of a mid-sized contractor’s cash gone on day one, with nothing left to chase the next tender.
Funded correctly — an advance-payment facility for mobilisation, an IPC-backed line for the certified progress, trade finance for the major procurement, and a retention guarantee instead of frozen cash — the same project runs on the project’s own security. Your reserves stay free. Same contract, completely different risk profile, and a business that can actually grow into the next job.
Discuss Your Project Funding
If you have a large project on the horizon — or one already straining your cash — the time to structure the funding is before mobilisation, not after. We’ll map the project’s security, match it to the right facilities, and present it to the banks most likely to say yes.
Discuss Your Project Funding →APM Business Consultancy — Finance, Funding & Commercial Advisory for UAE Contractors · +971 52 315 6149 · info@accureonpower.com